1 years 11 months
April’20 – Mar’22
Critical Asset Maintenance and Analysis: Analyzed the Critical Assets in Bar & Rod Mill for maintenance to reduce the failure rate significantly.
Operational Improvement : Improved the operations of Pump Houses for continuous supply of industrial water to the Mill for the rolling process to enhance production by significant amount.
Reducing breakdowns enabling the Mill to generate a profit of INR 3.5 Crores per day.
8 years 3 months
Jan’12 – March’20
Condition Based Maintenance : Improved availability and reliability of the rotary machines to an uptime of 95% by vibration monitoring and vibration analysis.
? Risk Management : Ensured zero accidents during overhauling of Rotary Equipment by Hazards identification and risk analysis techniques
Cost Optimisation : Involved in bringing down the cost of repair by bringing down the vibrations level of the rotary equipment on the basis of vibration data analytics
4 years 3 month
Oct’07 – Dec’11
Operational Improvement and Problem Solving : Improved the operations of power and blowing station and solved day to day operational problem in the plant.
Industrial Standards and Safety Compliance : Ensured adherence to all industry standard operating procedures and safety standards in the plant
11 Months
Nov’06 – Sep’07
Preventive Maintenance of the various equipment in the Utilities Department at Jamnagar Refinery Complex.
Involved in the planning, scheduling and implementing the preventive maintenance activities of the various equipment.
Ensured availability of various equipment so that the supply of utilities such as compressed air, nitrogen, industrial water and process steam, remains unaffected.